Banff Harbour Update:
Shearwater Marine are mobilising and will be on site from Monday 26th June for approximately 6 to 8 weeks to set the East Pier concrete lower castings. During this time they will work 12 days on and 2 days off with dive operations restricting vessel movement.
The following schedule details when vessel movements are permitted including use of the public slipway at Banff from Monday 26th June:
Overnight between 7pm and 8am daily and every second weekend from 7pm the previous Friday evening up to 8am on the following Monday inclusive. Weekends of July 8-9th, 22-23rd, August 5-6th, 19-20th.
Shearwater marine will be operating diver flags at all other times during their working day (8am to 7pm).
Restrictions will be lifted when all diver operations are complete and we will update you all here and on the Harbour Notice Board.